Ongoing Projects
Project
M/S. Pritech, Phase II
Architect / Consultant
M/S. Thomas / M/S. Power Design
Work status
Completed
Fit-out duration in months
2 Years
Size (sq.ft)
8 Million & External Works HT
Power Obtained
26 MVA
Project
M/S. PTP III
Architect / Consultant
M/S. RSP / Prestige Constructions
Work status
Completed
Fit-out duration in months
1 Year 6 Months
Size (sq.ft)
4 Million
Power Obtained
24 MVA
Project
M/S. Silver Oak – Villas & Apartment
Architect / Consultant
Thomas / Sripeksha
Work status
Completed
Fit-out duration in months
1 1/2 Years
Size (sq.ft)
Internal & External
Power Obtained
3 MVA
Project
M/S. Prestige Trade Tower
Architect / Consultant
Thomas / Sripeksha
Work status
Ongoing
Fit-out duration in months
18 Months
Size (sq.ft)
Internal & External Electrical Works (Commercial)
Power Obtained
4 MVA
Project
M/S. Prestige Estates Projects Pvt. Ltd. – Hilton Hotel
Architect / Consultant
Thomas / AECOM
Work status
90%
Fit-out duration in months
18 Months
Size (sq.ft)
5-Star Hotel
Power Obtained
4 MVA
Project
RGA Infrastructure
Architect / Consultant
Thomas / Power Design
Work status
Completed
Fit-out duration in months
12 Months
Size (sq.ft)
4 Million
Power Obtained
14 MVA